WATER FOR NKHATA BAY TOWN IN MALAWI

BOOSTING TECHNICAL TRAINING IN CHAD

At the time of project preparation Nkhata Bay Town and surrounding areas in the north of Malawi faced water supply and sanitation constraints due to outdated infrastructure and growing demand. The water system, constructed in 1960 and last upgraded in 2003, had a treatment capacity of 1,450 m 3 /day against an estimated demand of 3,850 m 3 /day, resulting in intermittent supply, water losses associated with aging pipelines (in a national context where losses were estimated at about 33 percent), with limited storage capacity and high maintenance costs. These problems were becoming more acute as Nkhata Bay Town, with a population of 57,193 in a district of about 210,000 people, expanded as a port, tourism and transit center along Lake Malawi. The absence of a sewerage system meant reliance on on-site sanitation facilities, which became increasingly inadequate with urban growth, raising public health and environmental concerns. In September 2018, the OPEC Fund approved a US$12 million loan for the US$30.55 million Nkhata Bay Town Water Supply and Sanitation project co-financed with AfDB. The project aimed to enhance access to reliable US$ 12 m In 2018, the OPEC Fund approved a loan for the US$30.55 m Nkhata Bay Town Water Supply & Sanitation project

capacity strengthening of the Northern Region Water Board. Project implementation started in 2019 and ended in 2024.

The higher education and professional training system in Chad has not produced enough technically trained graduates to meet labor market needs, particularly in the health sector. Although the number of higher education institutions has expanded since 2000, in the 2010s only about 2–3 percent of students accessed higher education, while just 14 percent of graduates pursued scientific or technical specializations. These constraints were evident at the Abéché National Institute of Science and Technology (INSTA), a key provider of technical training for eastern and northern Chad, where the Department of Biomedical Science and Pharmacy lacked dedi- cated infrastructure and relied on shared classrooms and laboratories. The absence of specialized facili- ties limited practical training to about one hour per student per day and constrained student intake,

1,800 students The completed infrastructure enabled INSTA to expand its physical training capacity from about 1,200 to

OPEC Fund financing supported the rehabilitation and expansion of the Nkhata Bay Town water supply system. This included upgrades to the raw water intake pipeline from Lake Malawi, expansion of the water treatment plant, upgrading of transmission pipelines, construction of pumping stations and seven service reservoirs adding 8,050 m 3 of storage capacity, as well as the expansion of the distribution network with about 122 km of pipelines to enable approximately 5,000 new household connections and 85 communal water points. As a result of the project the share of households in the project area with access to drinking water increased from 37 percent at launch to 91.94 percent at comple- tion, exceeding the appraisal target of 90 percent. Service reliability also improved, with daily water avail- ability rising from an average of 16 hours to 23.5 hours per day. Using savings from the initial works contract the project expanded its scope and delivered 4,451 new household water connections (of the revised target of 5,000). In parallel, water treatment capacity increased substantially from 1,450 m 3 /day to 19,623 m 3 /day, supported by the installation of three raw water pumps, six water pumping stations, five reinforced-concrete reservoirs and one steel tank, as well as 46 km of trans- mission and 261 km of distribution networks. During implementation the project also supported 1,088 jobs, including 661 for youth and 253 for women.

capacity with a particular emphasis on biomedical and technical fields linked to health sector needs. Project implementation took place from 2016 to 2024 and delivered pedagogical and laboratory buildings, a lecture hall, technical and sports facilities, internal roadways, utilities and water supply infrastructure including two electricity back-up generators, a bore- hole and a water tower. These investments led to measurable improve- ments in training conditions, with the availability of practical training increasing from approximately 1 hour to about 2.5 hours per student per day and drinking water provision at the campus increasing from 25 to 75 cubic meters per day, both in line with the targets set at project appraisal. The completed infrastructure enabled INSTA to expand its physical training capacity from about 1,200 to 1,800 students between 2015 and 2024 and supported conditions to increase the annual output capacity of biomedical and pharmacy technicians from around 400 to 600. The ongoing phase II of the project, approved by the OPEC Fund in 2022, complements these investments through the construction of six accommodation buildings, a dining hall and related annex facilities.

US$ 6 m The OPEC Fund approved a loan for an US$18 million project co-financed with BADEA to expand INSTA

affecting the production of biomedical and pharmacy technicians at a time when health facilities faced shortages of qualified personnel.

In July 2015, the OPEC Fund approved a US$6 million loan for a US$18 million project co-financed with BADEA to expand INSTA. The project focused on expanding academic infrastructure and training

and sustainable drinking water supply and improve sanitation services through the rehabilitation and expansion of the existing water supply system, sanita- tion and hygiene interventions, as well as institutional

84

85

Powered by