RESULTS ANALYSIS METHODOLOGY AND LIMITATIONS
The largest share of public sector projects was concentrated in the transport sector. In the private sector more than half of the projects were implemented through financial institutions, followed by projects in the energy sector, reflecting the same trend observed over the past two years (Figure 3.4). Figure 3.4: Sector distribution of public vs. private sector projects analyzed 17+ 3+6+16+8+8+32+10+H % PUBLIC SECTOR Health Education Energy Transport 6 16 8 8 32 10 17 3 Agriculture Financial Sector Water & Sanitation Multisector 262+24+2+5+5+H+ % PRIVATE SECTOR Energy Multisector Health 62 24 2 5 5 2 Transport
METHODOLOGY
documentation primarily reports output-level achievements — such
To assess project results, the team in charge of producing this report
as kilometers of road constructed, megawatts installed, or schools
carried out a thorough desk review of approval, supervision and
built — while information on how these outputs were used is often
completion documents housed in the OPEC Fund’s internal systems,
limited. Consequently, data for intermediate outcome indicators,
complemented by publicly accessible completion documents from
including beneficiaries reached (for example, students enrolled,
co-financiers for projects finalized since 2018, as well as additional
patients treated or road users), have historically been incomplete,
Agriculture
data requested from clients as applicable. The results presented
although this gap is gradually improving.
in this report rely on data reported by OPEC Fund borrowers and,
COUNTING ACROSS DIFFERENT BENEFIT TYPES
when available, information provided by co-financing partners. This
Financial Sector
review informed the development of an expanded project results
Because results data do not distinguish individual beneficiaries, each
database, building on and enhancing earlier versions.
person is counted in every category of development benefit they
receive. For example, in a multi-sector project providing education,
DATA AVAILABILITY AND QUALITY
health and agricultural services to rural populations beneficiaries
Reporting has strengthened over time. Among the 46 non-trade
of each service would be counted separately, even if the same
projects reviewed, only six lacked results data (13 percent),
individuals benefited from all three. Similarly, for the cross-cutting
compared with 28 percent for last year’s report. Information on both
indicator “women benefited by economic empowerment initiatives”
target and actual results was available for 59 percent of the projects
female farmers who gain from agricultural economic empowerment
this year, up from 54 percent last year. For projects with both sets
activities would be counted both as farmers and as women bene-
of data, the average target achievement rate was 113 percent after
fiting from economic empowerment. As a result, the total number of
excluding one outlier (with a 1,617-percent achievement rate).
beneficiaries across all categories may exceed the total population
Variations in the availability and quality of project results data introduced some challenges for the review and may have affected the completeness of the results.
Overall, 59 percent of project-level indicators met or exceeded their
within a project’s area of influence.
targets. When possible, target values and actual results were drawn
CONVERSIONS AND OTHER DATA TREATMENT
from completion or supervision reports, acknowledging that targets
may have been adjusted during implementation. For projects
In several water and sanitation projects the reported number of
lacking updated targets in these documents, the analysis relied on
people with improved capacity to safely manage water and waste-
the targets established in the original approval documents.
water was converted into an estimated number of households by
dividing the number of people by the average national household
RESULTS SCOPE
size based on United Nations data (UN Database on Household Size
Consistent with the practices of other MDBs, the results presented
and Composition 2022). In addition, for one banking and financial
generally reflect the outcomes of the entire supported project
services project the reported outcome showed a negative change;
rather than solely those attributable to the OPEC Fund’s financing.
therefore, the result was recorded as zero.
Isolating OPEC Fund–specific contributions was, in most cases,
DATA LIMITATIONS
not feasible given the nature of the operations and the information
available. Nonetheless, when OPEC Fund resources were directed
The quality and comprehensiveness of completion reports was
toward clearly defined components with results distinguishable from
variable, posing challenges for the collection of results data. Some
the rest of the project, only those component-level outcomes were
examples for data limitations are as follows:
included.
• OPEC Fund projects have to date included limited gender-
OUTPUTS VS. OUTCOMES
disaggregated data: Of the 46 projects reviewed this year, only
Development results can reflect either the assets, products or
seven reported information on women beneficiaries.
services delivered by a project (outputs) or the broader effects that
• As in the previous report, several banking projects did not
arise from their use (outcomes). Although verifying the delivery
report the number of MSMEs financed.
of outputs is essential, assessing development effectiveness also
• Employment data were also inconsistently documented. Only
requires understanding whether these outputs have produced
10 of the 46 projects reviewed this year included information
the intended improvements in people’s lives. Collecting outcome
on jobs supported, although the actual number of projects
data is generally more challenging than gathering information on
generating or sustaining employment is believed to be consid-
outputs. For most OPEC Fund–supported projects, the available
erably higher.